What must a contractor receive before proceeding with a construction project?
Signs the contract
Submits the bid bond
Receives the notice of award
Receives the notice to proceed
The correct answer is: Receives the notice to proceed
A contractor must receive the notice to proceed before starting a construction project because this formal document serves as the official authorization from the owner or client to commence work. The notice to proceed outlines the start date and confirms that all preconstruction conditions, such as securing necessary permits, have been satisfied. This ensures that the contractor can proceed without delays or concerns regarding compliance, signaling that all contractual obligations have been met and that the project is ready to move forward. Receiving this notice is crucial as it provides the contractor with legal backing to begin the project, outlining the terms and expectations regarding the timeline and scope of work. This document is a significant step in the construction process, ensuring that both parties are aligned and prepared for the project ahead.